Two nuclear power plants to be commissioned by 2016

0
237

Two nuclear power plants, 340 MW each, are under construction at Chashma and are expected to be commissioned by 2016, with Chinese assistance.
Construction of these power plants became possible after a long-standing agreement, whereas three other nuclear power plants already commissioned in the country are performing well.
According to official sources, a major chunk of the Pakistan Atomic Energy Commission (PAEC) budget has been allocated to the two plants. PAEC envisages production of 8,800 MW by the year 2030 through nuclear power reactors, sources added.
“An amount of Rs 34.6 billion has been set aside for Chashma Nuclear Power Plants, C3 and C4. The total cost of these two projects is Rs 190 billion which will be partially funded by a Rs 136 billion Chinese loan,” said a source.
The government has so far spent Rs 62.4 billion on the mega project having a 660 MW generation capacity. With Rs 34.6 billion additional spending, the government will be able to complete almost half of the work by June 2013, an official said.
According to an official in the Ministry of Science and Technology, the government is harmonising efforts made in the energy sector by different ministries, departments and research centres by creating an Energy Council including heads of relevant organisations.
The council will be entrusted to advice on priority areas for Research and Development (R&D), management of resources and filling existing gaps.
Acquisition of technology for building nuclear power reactors through R&D and transfer of technology agreements is also in consideration, the official said.