Pakistan Today

Another unit of Neelum-Jhelum starts contributing to national grid

ISLAMABAD: The second unit of Neelum-Jhelum Hydropower Project has also started generating power on Tuesday to its maximum capacity of 242.25 MW, which is now being transmitted to the national grid.

As per contractual requirement, this unit will be initially on a 3-day and thereafter on a 30-day reliability period and will continuously generate power to its maximum capacity for the system, said a press release.

Earlier, this unit (Unit No.4) was put into operation during April, injected more than 1.3 million units of electricity during the test run. However, during the tests of this unit, some minor technical issues relating to this unit were emerged, which have now been rectified by the contractor.

The first unit, which was put on a 30-day reliability period on May 18, has successfully completed the tests. During this period, the unit continuously provided electricity to its maximum capacity i.e. 242.25 MW to the national grid, injecting more than 200 million units of electricity to the system in its reliability period. Subsequent to the completion of the reliability test, the first unit will now be shut down for making minor adjustments before taking over this unit by WAPDA. The process, which is a contractual obligation, may take about 10 days to complete. Thereafter, the contribution of Neelum-Jhelum Hydropower (i.e. from both the first and the second units) to the national grid will be doubled from 242.25 MW to 484.50 MW.

It is important to note that contrary to the media reports, the generating units of Neelum-Jhelum Hydropower Project are being completed according to the timelines and are passing through the required tests in accordance with the contractual obligations.

Neelum-Jhelum Hydropower Project has a cumulative generation capacity of 969 MW through its four units, with each of them having 242.25 MW capacity.

Exit mobile version